The top three floors have now been plastered and the kitchens fitted in studios 7,8 and 9. Tiling in the top floor bathrooms has also been completed and . . .
Oak flooring is being fitted to the 3rd floor studios and the kitchens will be installed early next week. The 2nd floor is now completely plastered and we . . .
All new windows have now been fitted and we have completed the plastering of the third floor walls and ceilings. We are currently laying 26mm acoustic . . .
Stainless steel mesh has been fitted over the block and brickwork to the chimney breast areas, to prevent any cracking through the rendering. Walls have . . .
The rear extension has been fully constructed and is now water tight, with the Coping stones on we are now ready to render. The new concrete windowsills . . .
It has been established that the render to the front elevation of the building is loose and in danger of falling off, this will need to be removed and the . . .
The parapet walls have been replaced & re-rendered on either side of the roof and re-roofing work has started to the rear of the property. All of the . . .
The roof is now being stripped and replaced, with new facia/soffits fitted to the front & rear of the building. All of the ventilation is now in place . . .
TSG have re-erected the rear scaffolding having completed the foundations and have started to rebuild the rear extension. All the steels are now in place . . .
The strip out of the property is now complete and the lower ground floor flat has been fully tanked to include the external meter cupboard. We will be . . .